- Implemented tests for domain and DNS management including adding domains, viewing DNS records, and SSL certificate management. - Created monitoring and audit tests for log display, filtering, searching, and export functionality. - Developed backup and recovery tests covering manual backups, scheduling, restoration, and data integrity verification. - Added emergency operations tests for emergency token usage, break-glass recovery procedures, and security module management. - Included a comprehensive README for the UAT test suite detailing test coverage, execution instructions, and success criteria.
617 lines
22 KiB
Markdown
617 lines
22 KiB
Markdown
# Phase 4: UAT & Integration Testing Plan
|
||
|
||
**Date:** February 10, 2026
|
||
**Status:** READY FOR EXECUTION ✅
|
||
**Confidence Level:** 85% (based on Phase 2-3 baseline + test creation complete)
|
||
**Estimated Duration:** 2-3 hours (execution only; test writing completed)
|
||
**Test Coverage:** 110 comprehensive test cases (70 UAT + 40 integration)
|
||
**Test Files Status:** ✅ All test suites created and ready in `/tests/phase4-*/`
|
||
**Note:** Regression tests (CVE/upstream dependency tracking) handled by CI security jobs, not Phase 4 UAT
|
||
|
||
---
|
||
|
||
## Executive Summary
|
||
|
||
Phase 4 is the final validation milestone before production beta release. This plan provides:
|
||
|
||
1. **User Acceptance Testing (UAT)** - 70 real-world workflow tests validating that end-users can perform all major operations
|
||
2. **Integration Testing** - 40 multi-component tests ensuring system components work together correctly
|
||
3. **Production Readiness** - Final checklists and go/no-go gates before beta launch
|
||
|
||
**Note on Security Regression Testing:** CVE tracking and upstream dependency regression testing is handled by dedicated CI jobs (Trivy scans, security integration tests run with modules enabled). Phase 4 UAT focuses on feature validation with security modules disabled for isolated testing.
|
||
|
||
### Success Criteria
|
||
|
||
- ✅ All 70 UAT tests passing (core workflows functional)
|
||
- ✅ All 40 integration tests passing (components working together)
|
||
- ✅ Zero CRITICAL/HIGH security vulnerabilities (Trivy scan)
|
||
- ✅ Production readiness checklist 100% complete
|
||
- ✅ Performance metrics within acceptable ranges
|
||
- ✅ Documentation updated and complete
|
||
|
||
### Go/No-Go Decision
|
||
|
||
| Outcome | Criteria | Action |
|
||
|---------|----------|--------|
|
||
| **GO** | All tests passing, zero CRITICAL/HIGH vulns, checklist complete | Proceed to beta release |
|
||
| **CONDITIONAL** | Minor issues found (non-blocking tests), easy remediation | Fix issues, retest, then GO |
|
||
| **NO-GO** | Critical security issues, major test failures, architectural problems | Stop, remediate, restart Phase 4 |
|
||
|
||
---
|
||
|
||
## Risk Assessment & Mitigation
|
||
|
||
### TOP 3 IDENTIFIED RISKS
|
||
|
||
#### Risk #1: Test Implementation Delay → **RESOLVED ✅**
|
||
- **Status:** All 110 test files created and ready (70 UAT + 40 integration)
|
||
- **Previous Impact:** Could extend Phase 4 from 3-5 hours → 18-25 hours
|
||
- **Mitigation Applied:** Pre-write all test suites before Phase 4 execution
|
||
- **Current Impact:** ZERO - Tests ready to run
|
||
|
||
#### Risk #2: Security Module Regression (Handled by CI)
|
||
- **Status:** MITIGATED - Delegated to CI security jobs
|
||
- **Impact:** Phase 3 security modules could be broken by future changes
|
||
- **Mitigation:**
|
||
1. Dedicated CI jobs test security with modules **enabled**: `cerberus-integration.yml`, `waf-integration.yml`, `rate-limit-integration.yml`, `crowdsec-integration.yml`
|
||
2. CVE tracking and upstream dependency changes monitored by Trivy + security scanning
|
||
3. Phase 4 UAT runs with security modules **disabled** for isolated feature testing
|
||
4. Security regression detection: Automated by CI pipeline, not Phase 4 responsibility
|
||
- **Monitoring:** CI security jobs run on each commit; Phase 4 focuses on feature validation
|
||
|
||
#### Risk #3: Concurrency Issues Missed by Low Test Concurrency
|
||
- **Status:** MITIGATED - Increased concurrency levels
|
||
- **Impact:** Production race conditions not caught in testing
|
||
- **Mitigation Applied:** Updated INT-407, INT-306 to use 20+ and 50+ concurrent operations respectively
|
||
- **Current Status:** Updated in integration test files (INT-407: 2→20, INT-306: 5→50)
|
||
|
||
### STOP-AND-INVESTIGATE TRIGGERS
|
||
|
||
```
|
||
IF UAT tests <80% passing THEN
|
||
PAUSE and categorize failures:
|
||
- CRITICAL (auth, login, core ops): Fix immediately, re-test
|
||
- IMPORTANT (features): Documented as known issue, proceed
|
||
- MINOR (UI, formatting): Noted for Phase 5, proceed
|
||
END IF
|
||
|
||
IF Integration tests have race condition failures THEN
|
||
Increase concurrency further, re-run
|
||
May indicate data consistency issue
|
||
END IF
|
||
|
||
IF ANY CRITICAL or HIGH security vulnerability discovered THEN
|
||
STOP Phase 4
|
||
Remediate vulnerability
|
||
Re-run security scan
|
||
Do NOT proceed until 0 CRITICAL/HIGH
|
||
END IF
|
||
|
||
IF Response time >2× baseline (e.g., Login >300ms vs <150ms baseline) THEN
|
||
INVESTIGATE:
|
||
- Database performance issue
|
||
- Memory leak during test
|
||
- Authentication bottleneck
|
||
Optimize and re-test
|
||
END IF
|
||
```
|
||
|
||
---
|
||
|
||
## Performance Baselines
|
||
|
||
### Target Response Times (Critical Paths)
|
||
|
||
| Endpoint | Operation | Target (P99) | Measurement Method | Alert Threshold |
|
||
|----------|-----------|--------------|-------------------|------------------|
|
||
| `/api/v1/auth/login` | Authentication | <150ms | Measure request → response | >250ms (fail) |
|
||
| `/api/v1/users` | List users | <250ms | GET with pagination | >400ms (investigate) |
|
||
| `/api/v1/proxy-hosts` | List proxies | <250ms | GET with pagination | >400ms (investigate) |
|
||
| `/api/v1/users/invite` | Create user invite | <200ms | Was 5-30s; verify async | >300ms (regressed) |
|
||
| `/api/v1/domains` | List domains | <300ms | GET full list | >500ms (investigate) |
|
||
| `/api/v1/auth/refresh` | Token refresh | <50ms | POST to refresh endpoint | >150ms (investigate) |
|
||
| Backup Operation | Create full backup | <5min | Time from start → complete | >8min (investigate) |
|
||
| Restore Operation | Restore from backup | <10min | Time from restore → operational | >15min (investigate) |
|
||
|
||
### Resource Usage Baselines
|
||
|
||
| Metric | Target | Max Alert | Measurement |
|
||
|--------|--------|-----------|-------------|
|
||
| Memory Usage | <500MB steady | >750MB | `docker stats charon-e2e` during tests |
|
||
| CPU Usage (peak) | <70% | >90% | `docker stats` or `top` in container |
|
||
| Database Size | <1GB | >2GB | `du -sh /var/lib/postgresql` |
|
||
| Disk I/O | Normal patterns | >80% I/O wait | `iostat` during test |
|
||
|
||
### Measurement Implementation
|
||
|
||
```typescript
|
||
// In each test, measure response time:
|
||
const start = performance.now();
|
||
const response = await page.request.get('/api/v1/users');
|
||
const duration = performance.now() - start;
|
||
console.log(`API Response time: ${duration.toFixed(2)}ms`);
|
||
|
||
// Expected: ~100-250ms
|
||
// Alert if: >400ms
|
||
```
|
||
|
||
### Performance Regression Detection
|
||
|
||
**If any metric exceeds baseline by 2×:**
|
||
1. Run again to rule out transient slowdown
|
||
2. Check system load (other containers running?)
|
||
3. Profile: Database query slowness? API endpoint issue? Network latency?
|
||
4. If confirmed regression: Stop Phase 4, optimize, re-test
|
||
|
||
---
|
||
|
||
## Browser Testing Strategy
|
||
|
||
### Scope & Rationale
|
||
|
||
**Phase 4 Browser Coverage: Firefox ONLY (Primary QA Browser)**
|
||
|
||
```
|
||
Browser Testing Strategy:
|
||
├── Regression Tests (Phase 2.3 + 3)
|
||
│ └── Firefox only (API-focused, not browser-specific)
|
||
│ └── Rationale: Security/performance tests, browser variant not critical
|
||
│
|
||
├── UAT Tests (User workflows)
|
||
│ └── Firefox only (primary user flow validation)
|
||
│ └── Rationale: Test coverage in hours; multi-browser testing deferred to Phase 5
|
||
│ └── Exception: Top 5 critical UAT tests (login, user create, proxy create, backup, security)
|
||
│ may spot-check on Chrome if time permits
|
||
│
|
||
├── Integration Tests (Component interactions)
|
||
│ └── Firefox only (API-focused, data consistency tests)
|
||
│ └── Rationale: Not visual/rendering tests; browser independence assumed
|
||
│
|
||
└── NOT in Phase 4 scope (defer to Phase 5):
|
||
├── Chrome (Chromium-based compliance)
|
||
├── Safari/WebKit (edge cases, rendering)
|
||
├── Mobile browser testing
|
||
└── Low-bandwidth scenarios
|
||
```
|
||
|
||
### Execution Command
|
||
|
||
**Phase 4 Test Execution (Firefox only):**
|
||
```bash
|
||
cd /projects/Charon
|
||
echo "Step 1: Rebuild E2E environment"
|
||
.github/skills/scripts/skill-runner.sh docker-rebuild-e2e
|
||
|
||
echo "Step 2: Run regression tests"
|
||
npx playwright test tests/phase4-regression/ --project=firefox
|
||
|
||
echo "Step 3: Run UAT tests"
|
||
npx playwright test tests/phase4-uat/ --project=firefox
|
||
|
||
echo "Step 4: Run integration tests (serial for concurrency tests)"
|
||
npx playwright test tests/phase4-integration/ --project=firefox --workers=1
|
||
```
|
||
|
||
### Why NOT Multi-Browser in Phase 4?
|
||
|
||
| Reason | Justification | Timeline Impact |
|
||
|--------|---------------|------------------|
|
||
| **Time constraint** | 145 tests × 3 browsers = 435 test runs (would extend 3-5 hr to 9-15 hrs) | Would exceed Phase 4 window |
|
||
| **Test focus** | UAT/Integration are functional, not rendering-specific | Browser variance minimal for these tests |
|
||
| **CI/CD already validates** | `.github/workflows/` runs multi-browser tests post-Phase4 | Redundant in Phase 4 |
|
||
| **MVP scope** | Phase 4 is feature validation, Phase 5 is cross-browser hardening | Proper sequencing |
|
||
| **Production**: Phase 5 will include| Chrome/Safari spot-checks + full multi-browser CI | Comprehensive coverage post-Phase 4 |
|
||
|
||
### If Additional Browsers Needed:
|
||
|
||
**Chrome spot-check (5 critical tests only):**
|
||
```bash
|
||
# ONLY if Phase 4 ahead of schedule:
|
||
npx playwright test tests/phase4-uat/02-user-management.spec.ts --project=chromium
|
||
npx playwright test tests/phase4-uat/03-proxy-host-management.spec.ts --project=chromium
|
||
npx playwright test tests/phase4-uat/07-backup-recovery.spec.ts --project=chromium
|
||
npx playwright test tests/phase4-integration/01-admin-user-e2e-workflow.spec.ts --project=chromium
|
||
npx playwright test tests/phase4-regression/phase-3-security-gates.spec.ts --project=chromium
|
||
```
|
||
|
||
**WebKit (NOT recommended for Phase 4):** Deferred to Phase 5
|
||
|
||
---
|
||
|
||
## Updated Test File Locations
|
||
|
||
### Test Files Created & Ready ✅
|
||
|
||
**Location:** `/projects/Charon/tests/phase4-*/`
|
||
|
||
```
|
||
tests/
|
||
├── phase4-uat/ (70 UAT tests, 8 feature areas)
|
||
│ ├── 01-admin-onboarding.spec.ts (8 tests)
|
||
│ ├── 02-user-management.spec.ts (10 tests)
|
||
│ ├── 03-proxy-host-management.spec.ts (12 tests)
|
||
│ ├── 04-security-configuration.spec.ts (10 tests)
|
||
│ ├── 05-domain-dns-management.spec.ts (8 tests)
|
||
│ ├── 06-monitoring-audit.spec.ts (8 tests)
|
||
│ ├── 07-backup-recovery.spec.ts (9 tests)
|
||
│ ├── 08-emergency-operations.spec.ts (5 tests)
|
||
│ └── README.md
|
||
│
|
||
├── phase4-integration/ (40 integration tests, 7 scenarios)
|
||
│ ├── 01-admin-user-e2e-workflow.spec.ts (7 tests)
|
||
│ ├── 02-waf-ratelimit-interaction.spec.ts (5 tests)
|
||
│ ├── 03-acl-waf-layering.spec.ts (4 tests)
|
||
│ ├── 04-auth-middleware-cascade.spec.ts (6 tests)
|
||
│ ├── 05-data-consistency.spec.ts (8 tests)
|
||
│ ├── 06-long-running-operations.spec.ts (5 tests)
|
||
│ ├── 07-multi-component-workflows.spec.ts (5 tests)
|
||
│ └── README.md
|
||
|
||
TOTAL: 110 tests ready to execute
|
||
NOTES:
|
||
- Security/CVE regression testing (Phase 2.3 fixes, Phase 3 gates) handled by CI jobs
|
||
- Trivy scans and security integration tests run on each commit with modules enabled
|
||
- Phase 4 focuses on feature UAT and data consistency with security modules disabled
|
||
```
|
||
|
||
---
|
||
|
||
## Execution Strategy
|
||
|
||
### Test Execution Order
|
||
|
||
Phase 4 tests should execute in this order to catch issues early:
|
||
|
||
1. **UAT Tests** (70 tests) - ~60-90 min
|
||
- ✅ Admin Onboarding (8 tests) - ~10 min
|
||
- ✅ User Management (10 tests) - ~15 min
|
||
- ✅ Proxy Hosts (12 tests) - ~20 min
|
||
- ✅ Security Configuration (10 tests) - ~15 min
|
||
- ✅ Domain Management (8 tests) - ~15 min
|
||
- ✅ Monitoring & Audit (8 tests) - ~10 min
|
||
- ✅ Backup & Recovery (9 tests) - ~15 min
|
||
- ✅ Emergency Operations (5 tests) - ~8 min
|
||
|
||
2. **Integration Tests** (40 tests) - ~45-60 min
|
||
- Multi-component workflows
|
||
- Data consistency verification
|
||
- Long-running operations
|
||
- Error handling across layers
|
||
|
||
3. **Production Readiness Checklist** - ~30 min
|
||
- Manual verification of 45 checklist items
|
||
- Documentation review
|
||
- Security spot-checks
|
||
|
||
**Note:** Phase 2.3 fixes and Phase 3 security gates are validated by CI security jobs (run with security modules enabled), not Phase 4 UAT.
|
||
|
||
### Parallelization Strategy
|
||
|
||
To reduce total execution time, run independent suites in parallel where possible:
|
||
|
||
**Can Run Parallel:**
|
||
- UAT suites are independent (no data dependencies)
|
||
- Different user roles can test simultaneously
|
||
- Integration tests can run after UAT
|
||
- Regression tests must run first (sequential)
|
||
|
||
**Must Run Sequential:**
|
||
- Phase 2.3 regression (validates state before other tests)
|
||
- Phase 3 regression (validates state before UAT)
|
||
- Auth/user tests before authorization tests
|
||
- Setup operations before dependent tests
|
||
|
||
**Recommended Parallelization:**
|
||
```
|
||
Phase 2.3 Regression [████████████] 15 min (sequential)
|
||
Phase 3 Regression [████████████] 10 min (sequential)
|
||
UAT Suite A & B [████████████] 50 min (parallel, 2 workers)
|
||
UAT Suite C & D [████████████] 50 min (parallel, 2 workers)
|
||
Integration Tests [████████████] 60 min (4 parallel suites)
|
||
─────────────────────────────────────────────
|
||
Total Time: ~90 min (vs. 225 min if fully sequential)
|
||
```
|
||
|
||
### Real-Time Monitoring
|
||
|
||
Monitor these metrics during Phase 4 execution:
|
||
|
||
| Metric | Target | Action if Failed |
|
||
|--------|--------|------------------|
|
||
| Test Pass Rate | >95% | Stop, investigate failure |
|
||
| API Response Time | <200ms p99 | Check performance, DB load |
|
||
| Error Rate | <0.1% | Check logs for errors |
|
||
| Security Events Blocked | >0 (if attacked) | Verify WAF/ACL working |
|
||
| Audit Log Entries | >100 per hour | Check audit logging active |
|
||
| Memory Usage | <500MB | Monitor for leaks |
|
||
| Database Size | <1GB | Check for unexpected growth |
|
||
|
||
### Success/Fail Decision Criteria
|
||
|
||
**PASS (Proceed to Beta):**
|
||
- ✅ All Phase 2.3 regression tests passing
|
||
- ✅ All Phase 3 regression tests passing
|
||
- ✅ ≥95% of UAT tests passing (≥48-76 of 50-80)
|
||
- ✅ ≥90% of integration tests passing (≥27-45 of 30-50)
|
||
- ✅ Trivy: 0 CRITICAL, 0 HIGH (in app code)
|
||
- ✅ Production readiness checklist ≥90% complete
|
||
- ✅ No data corruption or data loss incidents
|
||
|
||
**CONDITIONAL (Review & Remediate):**
|
||
- ⚠️ 80-95% of tests passing, but non-blocking issues
|
||
- ⚠️ 1-2 MEDIUM vulnerabilities (reviewable, documented)
|
||
- ⚠️ Minor documentation gaps (non-essential for core operation)
|
||
- **Action:** Fix issues, rerun affected tests, re-evaluate
|
||
|
||
**FAIL (Do Not Proceed):**
|
||
- ❌ <80% of tests passing (indicates major issues)
|
||
- ❌ CRITICAL or HIGH security vulnerabilities (in app code)
|
||
- ❌ Data loss or corruption incidents
|
||
- ❌ Auth/authorization not working
|
||
- ❌ WAF/security modules not enforcing
|
||
- **Action:** Stop Phase 4, remediate critical issues, restart from appropriate phase
|
||
|
||
### Escalation Procedure
|
||
|
||
If tests fail, escalate in this order:
|
||
|
||
1. **Developer Review** (30 min)
|
||
- Identify root cause in failure logs
|
||
- Determine if fix is quick (code change) or structural
|
||
|
||
2. **Architecture Review** (if needed)
|
||
- Complex failures affecting multiple components
|
||
- Potential architectural issues
|
||
|
||
3. **Security Review** (if security-related)
|
||
- WAF/ACL/rate limit failures
|
||
- Authentication/authorization issues
|
||
- Audit trail gaps
|
||
|
||
4. **Product Review** (if feature-related)
|
||
- Workflow failures that affect user experience
|
||
- Missing features or incorrect behavior
|
||
|
||
---
|
||
|
||
## Timeline & Resource Estimate
|
||
|
||
### Phase 4 Timeline (2-3 hours)
|
||
|
||
| Phase | Task | Duration | Resources |
|
||
|-------|------|----------|-----------|
|
||
| 1 | Rebuild E2E environment (if needed) | 5-10 min | 1 QA engineer |
|
||
| 2 | Run UAT test suite (70 tests) | 60-90 min | 2 QA engineers (parallel) |
|
||
| 3 | Run integration tests (40 tests) | 45-60 min | 2 QA engineers (parallel) |
|
||
| 4 | Production readiness review | 30 min | Tech lead + QA |
|
||
| 5 | Documentation & final sign-off | 20 min | Tech lead |
|
||
| **TOTAL** | **Phase 4 Complete** | **2-3 hours** | **2 QA + 1 Tech Lead** |
|
||
|
||
### Resource Requirements
|
||
|
||
- **QA Engineers:** 2 (for parallel test execution)
|
||
- **Tech Lead:** 1 (for review and go/no-go decisions)
|
||
- **Infrastructure:** Docker environment, CI/CD system
|
||
- **Tools:** Playwright, test reporters, monitoring tools
|
||
|
||
### Pre-Phase 4 Preparation (1 hour)
|
||
|
||
- [ ] Review Phase 2.3 fix details (crypto, async email, token refresh)
|
||
- [ ] Review Phase 3 security test infrastructure
|
||
- [ ] Prepare production readiness checklist
|
||
- [ ] Set up test monitoring and alerting
|
||
- [ ] Create test failure log templates
|
||
- [ ] Brief team on Phase 4 plan
|
||
|
||
---
|
||
|
||
## Go/No-Go Decision Matrix
|
||
|
||
### Decision Authority
|
||
|
||
- **Phase 4 Authorization:** Technical Lead (sole authority)
|
||
- **Escalation:** Product Manager (if contested)
|
||
- **Final Approval:** Engineering Manager
|
||
|
||
### Decision Criteria
|
||
|
||
#### Criteria 1: Test Pass Rates
|
||
|
||
| Test Category | Phase | Pass Rate | Decision |
|
||
|---------------|-------|-----------|----------|
|
||
| Regression | 2.3 | 100% | **GO** |
|
||
| Regression | 3 | 100% | **GO** |
|
||
| UAT | 4 | ≥95% | **GO** |
|
||
| Integration | 4 | ≥90% | **GO** |
|
||
| All Combined | - | ≥92% | **GO** |
|
||
| All Combined | - | 80-92% | **CONDITIONAL** |
|
||
| All Combined | - | <80% | **NO-GO** |
|
||
|
||
#### Criteria 2: Security Vulnerabilities
|
||
|
||
| Severity | App Code | Dependencies | Decision |
|
||
|----------|----------|--------------|----------|
|
||
| CRITICAL | 0 allowed | 0 allowed | **REQUIRED** |
|
||
| HIGH | 0 allowed | Document & review | **REQUIRED** |
|
||
| MEDIUM | Assess risk | Acceptable | **OK** |
|
||
| LOW | Acceptable | Acceptable | **OK** |
|
||
|
||
#### Criteria 3: Production Checklist
|
||
|
||
| Category | Items Complete | Status |
|
||
|----------|-----------------|--------|
|
||
| Deployment | ≥13/15 | **GO** |
|
||
| Documentation | ≥10/12 | **GO** |
|
||
| Security | 10/10 | **REQUIRED** |
|
||
| Performance | ≥6/8 | **CONDITIONAL** |
|
||
| Release | 10/10 | **REQUIRED** |
|
||
|
||
#### Criteria 4: Data Integrity
|
||
|
||
| Aspect | Status | Decision |
|
||
|--------|--------|----------|
|
||
| No data loss | ✅ Verified | **GO** |
|
||
| No data corruption | ✅ Verified | **GO** |
|
||
| Backups working | ✅ Verified | **GO** |
|
||
| Restore successful | ✅ Verified | **GO** |
|
||
| User isolation intact | ✅ Verified | **GO** |
|
||
|
||
### Sample Decision Scenarios
|
||
|
||
**Scenario 1: All Tests Pass, No Issues**
|
||
```
|
||
Phase 2.3 Regression: 20/20 ✅
|
||
Phase 3 Regression: 15/15 ✅
|
||
UAT: 75/80 (93%) ✅
|
||
Integration: 48/50 (96%) ✅
|
||
Security Scan: 0 CRITICAL, 0 HIGH ✅
|
||
Checklist: 44/45 items ✅
|
||
Data Integrity: All verified ✅
|
||
───────────────────────────
|
||
DECISION: ✅ GO FOR BETA RELEASE
|
||
```
|
||
|
||
**Scenario 2: Few UAT Failures, No Security Issues**
|
||
```
|
||
Phase 2.3 Regression: 20/20 ✅
|
||
Phase 3 Regression: 15/15 ✅
|
||
UAT: 68/80 (85%) ⚠️ (7 failures non-blocking)
|
||
Integration: 45/50 (90%) ✅
|
||
Security Scan: 0 CRITICAL, 0 HIGH ✅
|
||
Checklist: 42/45 items ⚠️
|
||
Data Integrity: All verified ✅
|
||
───────────────────────────
|
||
DECISION: 🟡 CONDITIONAL
|
||
Action: Fix 7 failing UAT tests, verify no regressions, re-run
|
||
Expected: 1-2 hours remediation, then GO
|
||
```
|
||
|
||
**Scenario 3: Security Module Failure**
|
||
```
|
||
Phase 2.3 Regression: 20/20 ✅
|
||
Phase 3 Regression: 12/15 ❌ (ACL tests failing)
|
||
UAT: 60/80 (75%) ❌
|
||
Integration: 25/50 (50%) ❌
|
||
Security Scan: 2 CRITICAL (crypto issue) ❌
|
||
───────────────────────────
|
||
DECISION: ❌ NO-GO
|
||
Action: STOP Phase 4
|
||
- Investigate crypto issue (Phase 2.3 regression)
|
||
- Fix security module (Phase 3)
|
||
- Re-run regression tests
|
||
- Potentially restart Phase 4
|
||
Timeline: +4-8 hours
|
||
```
|
||
|
||
---
|
||
|
||
## Appendix
|
||
|
||
### A. Test Execution Commands
|
||
|
||
```bash
|
||
# Run all tests (sequential)
|
||
cd /projects/Charon
|
||
npx playwright test tests/phase3/ --project=firefox
|
||
|
||
# Run specific test category
|
||
npx playwright test tests/phase3/security-enforcement.spec.ts --project=firefox
|
||
|
||
# Run with debug output
|
||
npx playwright test --debug
|
||
|
||
# Generate HTML report
|
||
npx playwright show-report
|
||
|
||
# Run with specific browser
|
||
npx playwright test --project=chromium
|
||
npx playwright test --project=webkit
|
||
```
|
||
|
||
### B. Key Test Files Locations
|
||
|
||
- **Phase 2.3 Regression:** `/projects/Charon/tests/phase3/security-enforcement.spec.ts`
|
||
- **Phase 3 Regression:** `/projects/Charon/tests/phase3/*.spec.ts`
|
||
- **UAT Tests:** `/projects/Charon/tests/phase4-uat/` (to be created)
|
||
- **Integration Tests:** `/projects/Charon/tests/phase4-integration/` (to be created)
|
||
- **Test Utilities:** `/projects/Charon/tests/utils/`
|
||
- **Fixtures:** `/projects/Charon/tests/fixtures/`
|
||
|
||
### C. Infrastructure Requirements
|
||
|
||
**Docker Container:**
|
||
- Image: `charon:local` (built before Phase 4)
|
||
- Ports: 8080 (app), 2019 (Caddy admin), 2020 (emergency)
|
||
- Environment: `.env` with required variables
|
||
|
||
**CI/CD System:**
|
||
- GitHub Actions or equivalent
|
||
- Docker support
|
||
- Test result publishing
|
||
- Artifact storage
|
||
|
||
**Monitoring:**
|
||
- Real-time test progress tracking
|
||
- Error log aggregation
|
||
- Performance metrics collection
|
||
- Alert configuration
|
||
|
||
### D. Failure Investigation Template
|
||
|
||
When a test fails, use this template to document investigation:
|
||
|
||
```
|
||
Test ID: [e.g., UAT-001]
|
||
Test Name: [e.g., "Login page loads"]
|
||
Failure Time: [timestamp]
|
||
Environment: [docker/local/ci]
|
||
Browser: [firefox/chrome/webkit]
|
||
|
||
Expected Result: [e.g., "Login form displayed"]
|
||
Actual Result: [e.g., "404 Not Found"]
|
||
|
||
Error logs: [relevant logs from playwright reporter]
|
||
|
||
Root Cause Analysis:
|
||
- [ ] Code defect
|
||
- [ ] Test environment issue
|
||
- [ ] Test flakiness/race condition
|
||
- [ ] Environment variable missing
|
||
- [ ] Dependency issue (API down, DB locked, etc.)
|
||
|
||
Proposed Fix: [action to resolve]
|
||
Risk Assessment: [impact of fix]
|
||
Remediation Time: [estimate]
|
||
|
||
Sign-off: [investigator] at [time]
|
||
```
|
||
|
||
---
|
||
|
||
## References
|
||
|
||
- **Phase 2 Report:** [docs/reports/PHASE_2_FINAL_APPROVAL.md](docs/reports/PHASE_2_FINAL_APPROVAL.md)
|
||
- **Phase 3 Report:** [docs/reports/PHASE_3_FINAL_VALIDATION_REPORT.md](docs/reports/PHASE_3_FINAL_VALIDATION_REPORT.md)
|
||
- **Current Spec:** [docs/plans/current_spec.md](docs/plans/current_spec.md)
|
||
- **Security Instructions:** [.github/instructions/security-and-owasp.instructions.md](.github/instructions/security-and-owasp.instructions.md)
|
||
- **Testing Instructions:** [.github/instructions/testing.instructions.md](.github/instructions/testing.instructions.md)
|
||
|
||
---
|
||
|
||
## Sign-Off
|
||
|
||
**Document Status:** READY FOR TEAM REVIEW & APPROVAL
|
||
|
||
| Role | Name | Date | Signature |
|
||
|------|------|------|-----------|
|
||
| Technical Lead | [TO BE ASSIGNED] | 2026-02-10 | ☐ |
|
||
| QA Lead | [TO BE ASSIGNED] | 2026-02-10 | ☐ |
|
||
| Product Manager | [TO BE ASSIGNED] | 2026-02-10 | ☐ |
|
||
|
||
---
|
||
|
||
**Version:** 1.0
|
||
**Last Updated:** February 10, 2026
|
||
**Next Review:** Upon Phase 4 initiation or when significant changes occur
|
||
**Document Location:** `/projects/Charon/docs/plans/PHASE_4_UAT_INTEGRATION_PLAN.md`
|